Tarbela Extension 4 & 5

Lets not forget the original architect of two biggest dams of Pakistan (Tarbela & Mangla) with the help of World Bank & Asian Development Bank back in 1960s … the Great General Ayub Khan .. :k:

Another $51m to expedite Tarbela project completion

THE NEWSPAPER’S STAFF REPORTER — UPDATED a day ago

[TABLE=“class: media media–stretch one-whole palm–one-whole, width: 698”]

TARBELA: With the next general elections in mind, the government has decided to pay $51 million additional cost to Chinese contractors for advancing completion of 1,410MW Tarbela 4th extension project by eight months to June 2017.

Wapda and a consortium of M/s Sinohydro Group of China and Voith Hydro Germany and China signed a formal agreement at the Tarbela Dam on Thursday. The project acceleration programme is estimated to generate $300 million electricity during 2017, according to Wapda Chairman Zafar Mahmood.

Briefing journalists, Tarbela Dam General Manager Iqbal Siddiqui said the acceleration programme had been initiated on the directive of the prime minister.

The original T4 project was estimated to cost $928m, but the project authorities had been able to conclude the project contract at $651m. Since the project cost was much lower than estimates finalised in consultation with the World Bank ($840m), the bank not only approved $51m acceleration programme, but also agreed to divert about $150m, saving another 1,400MW for
Tarbela 5th Extension project which is expected to be completed by June 2018.

**The existing power house at Tarbela completed in 1974 has the total generation capacity of 3,478MW and it would go up to 4,888MW on completion of T4 in June 2017 and further to about 6,200MW by June 2018.
**

The T4 project is being constructed at Tunnel 4 of the dam which was originally intended for irrigation, but was later taken up for power generation as country’s electricity demand increased.

The country would get 3,840GWh every year from T4 and it would be available for power supply during peak demand months.
Sedimentation

Mr Siddiqui said that live storage capacity of Terbela reservoir had declined more than 33.5 per cent to 6.434 million acre feet (MAF) against its original capacity of 9.679 MAF because of sedimentation over the past 38 years.

Mr Siddiqui claimed that dredging of silt from the reservoir was almost impossible in view of technical and economic reasons. He said there was an option to flush out the silt through spillways, but it would have damaged Tarbela’s own turbines and also the 1,450MW Ghazi Barotha Hydropower projects downstream.

Another option involved dredging of silt but that was too expensive, estimated at $10-12 billion whereas the total cost of the Tarbela Dam construction was just $2.85bn.

He said the project was originally had a designed life of 30 years, but impressive dam management techniques was resulting in availability of more than 65pc storage capacity even after 38 years.

**
Tarbela-5**

Highlighting the Tarbela-5 (T5) project, Mr Zafar Memhood said that the PC-1 of the project would be approved by Executive Committee of the National Economic Council next month.

The T5 project is meant to generate 1,300MW to 1,400MW after its completion in **2018. **The study for the project has been completed with $2.9m financing by the World Bank.

The study allows us to install turbines in Tunnel 5 that will generate electricity up to 1,400MW, lifting the total electricity generation capacity of the Tarbela Dam up to 6,200MW.

“We have conditional offers of euro 300 million for financing the T5 each from Austrian government and M/s Voith Germany if we agree to award them contract,” he said.
*

Published in Dawn March 7th , 2015*

Re: Tarbela Extension 4 & 5

World Bank agrees to finance Tarbela’s extension

By Shahbaz Rana
Published: November 20, 2015

http://i1.tribune.com.pk/wp-content/uploads/2015/11/994891-Tarbela-1447955094-784-640x480.JPG

***Pakistan has qualified for the IBRD funding after a gap of about three years due to improvement in its foreign currency reserves. PHOTO: FILE


ISLAMABAD: The World Bank has affirmed its financial assistance for the **1,410-megawatt fifth extension of Tarbela hydroelectric power project **that will be built on existing infrastructure in order to enhance power generation capacity of the large reservoir to 6,300 MW.

Of the total project cost of about** $796 million,** the Washington-based lender’s exact share has not yet been determined. However, it will be a minimum $326 million including savings of $126 million from the fourth extension programme, say officials.
](http://tribune.com.pk/story/925983/fruitful-weather-power-output-increases-by-100mw-in-tarbela/)

“Work on the fifth extension will be completed in three and a half years from the date of inception,” said a senior official of the Water and Power Development Authority (Wapda).
The World Bank confirmed its financing support to the Economic Affairs Division in September this year, said Tarbela Dam General Manager Iqbal Masood Siddiqui. However, exact modalities of the funding have to be finalised.

The Economic Affairs Division had approached the bank, seeking assistance to implement the project.

The bank is expected to give $500 million from its relatively expensive financing arm, the International Bank for Reconstruction and Development (IBRD). The loan could be approved next year, which will facilitate the award of civil works contract.

Of the $500 million, $200 million could be given for the Tarbela fifth extension and the remaining will go to other federal and provincial projects.

The country can also opt for $200 million from Oekb Export Credit Bank of Austria, but the Ministry of Finance has reservations about the cost of loan, which is tied to the supply of turbines by an Austrian manufacturer.

Pakistan has qualified for the IBRD funding after a gap of about three years due to improvement in its foreign currency reserves.

The foreign exchange component will constitute 85% of the project cost. Siddiqui, however, said there was still a financing gap, which would be either bridged by increasing Wapda’s share in financing or by obtaining a loan from other sources.

The Central Development Working Party has cleared the fifth extension project at a cost of $795.8 million and it will now be tabled for approval of the Executive Committee of National Economic Council.

The fifth extension was among half a dozen hydroelectric and nuclear power projects with a cumulative generation capacity of 14,700MW, which would be completed between 2018 and 2023, said Finance Minister Ishaq Dar on Thursday.

The existing tunnel-5 of Tarbela Dam would be converted into a power tunnel without affecting its capability of water release for irrigation purposes, said Siddiqui while briefing about the fourth extension’s current status and future roadmap.

The GM said three units with a capacity of 470MW each would be constructed on the tunnel-5, which was on the left bank of Indus River.

The installed capacity of the 3,478 MW Tarbela hydroelectric power stations will increase to 6,300 MW after completion of the ongoing fourth extension and the planned fifth extension.

Work on the fourth extension has been undertaken at tunnel-4 of the dam, which was originally intended for irrigation purposes, but was later taken up for power generation as the country’s electricity demand increased. The World Bank gave $840 million for the fourth extension.
](http://tribune.com.pk/story/834670/world-bank-has-approved-construction-of-five-power-projects-in-pakistan-dar/)
The government has already signed a $51-million Tarbela-IV acceleration plan with a consortium of Sinohydro Group of China and Voith Hydro Germany to complete the task in June 2017 – seven months ahead of schedule.

The purpose of the acceleration plan was to fully take advantage of the peak flow season in 2017, which would help generate $300 million worth of additional electricity, he added.
*
Published in The Express Tribune, November 20[SUP]th[/SUP], 2015.*

Re: Tarbela Extension 4 & 5

Mangla refurbishment to enhance power generation capacity to 1,310 MW

2 DAYS AGO BY APP

http://cache.pakistantoday.com.pk/2012/11/ManglaDam.jpg

The Mangla Refurbishment Project being implemented by the Water and Power Development Authority (WAPDA) will increase the generation capacity of Mangla Hydel Power Station from 1,000 mega watt (MW) to 1,310 MW.

Official sources told APP that the Mangla Refurbishment Project would be completed in three phases with approved PC-1 amounting to Rs 52,224.3 million. On completion of the project, the existing installed capacity of Mangla Hydel Power Station would increase by another 310 MW with additional energy generation of 1,632 million units per annum, they said.

It is worth mentioning that Mangla Dam – the first-ever mega multi-purpose project in Pakistan comprising water storage and four power generating units of 100 MW each – was completed in 1967. Subsequently, units 5 and 6 were installed at the power house in 1974 and units 7 and 8 in 1981.

The Mangla Power House attained its maximum capacity, 1,000, MW in 1994 with an addition of units 9 and 10. Since its commissioning, the power house has contributed more than 210 billion units of low-cost electricity to the national grid.

The aging factor of the generating equipment and availability of additional water due to the raised Mangla Dam necessitated the refurbishment and up-gradation of Mangla Hydel Power Station.

The sources said there was a dire need of injecting low-cost hydroelectric power to the national gird to mitigate electricity shortages and reduce electricity tariff.
Therefore, it is imperative that Mangla Refurbishment Project be completed within the stipulated time frame.

The sources said the raised Mangla Dam filled to its maximum level of 1242 feet providing about three million acre feet of additional water for irrigation in addition to generating additional 620 million unit low-cost hydel electricity.

It is also worth mentioning that Mangla Hydel Power Station generated 6,496 million units of electricity in fiscal year 2014-15 and 5876 million units of electricity in 2013-14.

Mangla refurbishment to enhance power generation capacity to 1,310 MW | Pakistan Today

Re: Tarbela Extension 4 & 5

7100 MW Bunji Project: Wapda submits PC-1 to Planning Commission

November 16, 2015
RECORDER REPORT
http://www.brecorder.com/templates/br/images/emailButton.pnghttp://www.brecorder.com/templates/br/images/printButton.pnghttp://www.brecorder.com/templates/br/images/pdf_button.png

http://www.brecorder.com/images/br-black.gif

The Water and Power Development Authority (WAPDA) has submitted PC-I of the 7100-MW Bunji Hydropower Project located on Indus River 83 kms from Gilgit to the Planning Commission for approval. In a report to the Gilgit Baltistan government, WAPDA Chairman Zafar Mahmood said the Prime Minister attaches highest importance to the exploitation of hydropower potential, which exists in Gilgit-Baltistan.

According to Mahmood, Pakistan has the potential to produce 100,000 megawatts of hydroelectric power. Of this, the identified potential stands at 60,158MW, but only 6,919MW has so far been tapped.

He said the Indus Cascade, located in Gilgit-Baltistan and Khyber Pakhtunkhwa is the future’s energy corridor for Pakistan. PC-I of the 7100-MW Bunji Hydropower Project PC-I consisting of Land Acquisition, Preliminary activities, Civil & Electro Mechanical works has been sent to the Planning Commission for approval. PC-I of some of the projects on Indus Cascade are yet to be readied.

“To execute such as mega projects in private sector, WAPDA has submitted a policy to the Ministry of Water and Power for approval” he added.

The Chairman further said that on the directives of the Prime Minister, WAPDA is establishing two technical institutes one each at Chillas and Gilgit to train the locals in 3-year batches.

The manpower, trained so, will then be employed on WAPDA projects. However, the locals, who wish to study further after their training in these institutes, will also be given admission in WAPDA University to be set up at Tarbela. He said that WAPDA will provide technical support to Gilgit-Baltistan Government to help exploit their hydro potential.

The Chairman also briefed the G-B government about the matters relating to financial assistance of KFW of Germany and AFD of France for the 34-MW Harpo and the 40-MW Basho hydropower projects

Re: Tarbela Extension 4 & 5

ADB approves $1.4 billion loan to aid Pakistan’s power sector

By Shahbaz Rana
Published: November 20, 2015

http://i1.tribune.com.pk/wp-content/uploads/2015/11/995205-transformerx-1448018035-987-640x480.jpg

PHOTO: FILE

ISLAMABAD: The Asian Development Bank (ADB) on Friday approved a $1.4 billion loan for Pakistan for installation of smart electricity metres to monitor growing theft and facilitate the government in privatisation of power distribution companies and cutting power subsidies.
The board of directors of the Manila-based lending agency approved a multi-tranche facility of $990 million for installation of smart electricity metres and central billing systems, according to an announcement by the ADB.

The bank also approved another $400 million in budgetary support in return of the commitments to cut electricity subsidies, fast track privatisation and running the power sector on commercial basis.

Of the $1.4 billion, an amount of $400 million will be disbursed immediately in cash while the remaining amount will be released as the government makes progress in installation of smart electricity metres, the announcement read.

With the approval of two fresh loan programmes, the ADB’s lending for Pakistan’s power sector will increase to about $4 billion, deepening its interest in a sector that is marred by mismanagement, corruption and inefficiencies.

The statement further said that the $990 million multi-tranche Second Power Distribution Enhancement Investment Programme will be used for introducing an Advanced Electricity Metering Infrastructure (AMI) system for power distribution companies across the country.

“The new system will help reduce line losses, improve revenue collection and load management, and strengthen the financial viability of the sector,” it added.

However, the planning commission has expressed reservations over the proposed smart metres technology and its reliability and is seeking a certification that the system will work in Pakistan. Owing to these reasons, the executive committee of National Economic Council could not approve the first two smart metre projects that the authorities plan to implement in Lahore and Islamabad areas.

The ADB has an active loan portfolio of $5.5 billion in the public sector, which will now significantly increase after approval of two fresh programmes. On average, Pakistan takes about seven and half months to make a loan effective, which is a significant period, showing delays in regulatory approvals.

The ADB is already implementing three multi-financing facilities in power generation, renewable energy and the power distribution networks.

“Nearly 20% of generated electricity is lost due to high technical and commercial losses and measures like the installation of the AMI system are necessary to counter this,” said Adnan Tareen, senior energy specialist of the ADB.

The energy specialist further said that these two programmes will collectively help create a more efficient, transparent, modern and sustainable energy sector.

Pakistan is struggling with an ongoing power crisis, which is shaving off roughly 2% national output each year.

The ADB said that the power distribution companies were facing financial problems with customer tariffs being lower than the cost of service, and high system losses resulting in delayed payment to generating companies.
Despite making Rs 480 billion payments in June 2013, the circular debt has again increased to Rs 661 billion.
**

Budgetary support**

The ADB also approved $400 million in budgetary support under sustainable energy sector reforms programme. The approval came on the heels of $500 million loan that the World Bank gave last week for the energy sector reforms.

The bank has diverted over $110 million project funds towards the budgetary support that it had earlier earmarked for two hydro sector projects in Gilgit Baltistan. The funds remained unutilised for many years.

The ADB said that the budgetary support will help policy measures to address extensive debts in the electricity sector, as well as further market reforms to improve the efficiency of public sector power companies and to encourage competition through more private sector participation.

The specific outputs attached with $400 million loan are managing tariffs and subsidies by implementing clear policies on tariffs and subsidies that are targeted at low-income customers, ensuring policy implementation and limiting discretionary policy decisions in tariff approval and implementation.

Re: Tarbela Extension 4 & 5

3,500MW wind energy to be added to national grid by 2018

22 HOURS AGO BY APP

http://cache.pakistantoday.com.pk/Electric.jpg

The Alternate Energy Development Board (AEDB) has embarked upon an ambitious plan to enhance the energy mix by up to 20-25 per cent by adding 3,000-3,500MW of wind-based electricity to the national grid by 2018.

“Out of this, 1,396MW of electricity will be added to the system by 2017 as the AEDB would complete several projects initiated for alternate power generation by then,” AEDB Chief Executive Officer (CEO) Amjad A. Awan said in an interview on Thursday.

Awan said that currently wind projects of 255.4MW were operational across the country including FFC Energy (49.5MW) Jhampir, ZorluEnerji Pakistan (56.4MW) Jhampir, Three Gorges First Wind Farm Pakistan (49.5MW) Jhampir, Foundation Wind Energy – II (50MW) Gharo and Foundation Wind Energy I (50MW) Gharo.

He said that 28 ongoing wind projects with combined campacity of 1,396.4MW would be completed by 2017, which would play a major role in overcoming the energy crisis that the government is focusing on.

He said out of these, 9 projects (477MW) had achieved financial close and were under construction. These projects include Sapphire Wind Power Company (50MW), Yunus Energy (50MW), Metro Power Company (50MW) Jhampir, Tapal Wind Energy (30MW) Jhampir, Gul Wind Energy (50MW) Jhampir, United Energy Pakistan (99MW) Jhampir, Hydro China Dawood Power (50MW) Gharo, Master Wind Energy (50MW) Jhampir and Tenaga Generasi (50MW) Gharo.

He said that fourteen wind power projects with a cumulative capacity of 664MW were at different stages of project development and were expected to be completed by 2017-2018.

He said that power tariff for wind power projects had been reduced to 10.4 cents which indicated that this could prove a promising sector for future investments.

He said that Pakistan had a huge wind-power generation potential and if exploited properly, it could become a very lucrative and feasible source of alternate energy.

“Pakistan is naturally gifted in alternate energy resources and this has been identified by mapping assessment of wind, solar and biomass in the country through ESMAP’s (World Bank) assistance,” Awan said.

He said that wind potential had been evaluated at a huge scale in the country, “We have specifically identified wind corridors having power generation potential of 30,000MW.

He said that AEDB had identified the high-potential regions including in Southern Sindh, Balochistan and Punjab where electricity generation through wind had promising potential.

Re: Tarbela Extension 4 & 5

‘Tarbela 4th extension to be completed by June 2017’](‘Tarbela 4th extension to be completed by June 2017’)

By APP
Published: December 24, 2015

http://i1.tribune.com.pk/wp-content/uploads/2015/12/1015352-tarbeladamafpx-1450913369-898-640x480.jpg

PHOTO: AFP/FILE

TARBELA: The Tarbela 4th Extension Power Project worth $920 million will be completed by June 2017, adding 1,410 megawatts hydel electricity to the national grid.

Briefing journalists at the project site, Secretary Water and Power Muhammad Younas Daga said that the project was scheduled to be completed in 2018, but on the directives of the Prime Minister, work has been expedited and it will be fully functional by June 2017.

Daga said the World Bank was providing $840 million for the project. “Three units of 370MW each would be installed at the power house which would enhance the total electricity generation to 4,888 MW from the existing 3,478 MW.”

Referring to last year’s performance, the secretary said that work on a number of power projects has started and there would be no load-shedding by 2018.

He said that since November 2014, zero hour power load-shedding was being observed for the industrial sector. “Six to eight hours power load-management was being carried out in urban and rural areas respectively,” he said. However, he said that more load management was being carried out in areas of high losses.

Daga said that losses of power distribution companies were reduced to 18% while recoveries stood at 92.3% against the corresponding period of the previous year which was 88.6%.

He said 100% payment was being made to independent power producers and the circular debt was capped at Rs310 billion. Efforts were being made to further reduce the circular debt, he added.
**To a question, Daga said that an amount of Rs101 billion was allocated for land acquisition of Diamer Bhasha dam and 50% land had already been acquired so far.
**

“China has also shown interest in providing assistance to this mega project,” he added.

Regarding power projects under the China-Pakistan Economic Corridor (CPEC), the secretary said that power projects having 1,100 MW capacity would be ready in 2016, 1,650MW in 2017, 3,270 MW in 2018 and 2,250MW beyond 2018.

Regarding recent allegations of unmerited recruitments in power distribution companies (DISCOs), including Islamabad Electric Supply Company, the secretary said the IESCO’s chief executive officer has been sacked and the board of directors has been ordered to declare null and void all recruitments made in violation of merit policies.
*
Published in The Express Tribune, December 24[SUP]th[/SUP], 2015.*

Re: Tarbela Extension 4 & 5

This thread has been brought to you by Nawaz and Shahbaz misinformation department. Jiye nawaz.

Re: Tarbela Extension 4 & 5

ehsan bhai … plz dont say such things so openly on this forum :smokin2:

Re: Tarbela Extension 4 & 5

You should be paying money for posting these nonsense news items. I don’t know why administration here has tolerated this free advertising of stupid promotional news.